Sg. Selangor Phase 3 Water Supply Scheme

Semangar Water Supply Scheme

Bayan Baru Sewage Treatment Plant

Pulau Indah Sewage Treatment Plant

List of Major Projects


Flow Distribution Chamber

Sludge Thickening System

Sludge Storage Yard
      

Pulau Indah Sewage Treatment Plant          download the .pdf file

Location: Port Klang, Selangor, Malaysia
Client: Indah Water Konsortium
Consultant: KTA (Sarawak) Sdn. Bhd.
Capacity: 160,000 P.E.
Commencement Date: May 2000
Completion Date: May 2003

Another milestone to the wastewater segment of Hydro-Trent would be the sewage facility project for the Regional Sewage Treatment Plant & Associated Facility of Phase 2C Taman Perindustrian Pulau Indah in Klang.

The Pulau Indah Sewage Treatment Plant is located near the North Port in Port Klang. This facility is designed for a development project catering for a population of 160,000 P.E.

This sewerage system is one of the first in Malaysia where a vacuum system is utilised for the transfer of waste water into the treatment plant.

The scope of work for this project is to set up the CitectSCADA System for plant monitoring purpose. The extents of works for SCADA include the following: -

  1. To supply and install field control cabling from the field control panels to the SCADA system panels.
  2. To supply and install the Programmable Logic Controller (PLC), Remote Terminal Unit (RTU), controller, personal computer, printer, modem, system communication, cabling, etc.
  3. To supply, install and set up the licensed software for the SCADA.
  4. To design, configure and program the necessary graphics and Main-Machine-Interface (MMI) to the satisfaction of the client.
    - Graphic pictorials based on the process flow diagram and electrical single line diagram.
    - Trend displays each comprising of each analogue signal.
    - Guidance messages.
    - Alarm list.
    - Binary status list.
  5. To terminate the control cables in the field control panel and system cabinets after carrying out loop check.
  6. To carry out testing and commissioning of the complete SCADA system to the satisfaction of the client.
  7. To provide training for the operating maintenance personnel in all aspects of the operation and maintenance of SCADA equipment in the scope of supply.