Another milestone to the wastewater segment
of Hydro-Trent would be the sewage facility project for the Regional
Sewage Treatment Plant & Associated Facility of Phase 2C Taman
Perindustrian Pulau Indah in Klang.
The Pulau Indah Sewage Treatment Plant is located near the North
Port in Port Klang. This facility is designed for a development
project catering for a population of 160,000 P.E.
This sewerage system is one of the first in Malaysia where a vacuum
system is utilised for the transfer of waste water into the treatment
plant.
The scope of work for this project is to set up the CitectSCADA
System for plant monitoring purpose. The extents of works for SCADA
include the following: -
- To supply and install field control cabling from the field control
panels to the SCADA system panels.
- To supply and install the Programmable Logic Controller (PLC),
Remote Terminal Unit (RTU), controller, personal computer, printer,
modem, system communication, cabling, etc.
- To supply, install and set up the licensed software for the
SCADA.
- To design, configure and program the necessary graphics and
Main-Machine-Interface (MMI) to the satisfaction of the client.
- Graphic pictorials based on the process flow diagram and electrical
single line diagram.
- Trend displays each comprising of each analogue signal.
- Guidance messages.
- Alarm list.
- Binary status list.
- To terminate the control cables in the field control panel and
system cabinets after carrying out loop check.
- To carry out testing and commissioning of the complete SCADA
system to the satisfaction of the client.
- To provide training for the operating maintenance personnel
in all aspects of the operation and maintenance of SCADA equipment
in the scope of supply.
|